Water tanks flawed at Japanese nuclear plants, workers say

By Mari Yamaguchi
Associated Press

Print
Add This

TOKYO: When tons of radioactive water leaked from a storage tank at Fukushima’s crippled nuclear power plant and other containers hurriedly put up by the operator encountered problems, Yoshitatsu Uechi was not surprised. He wonders if one of the tanks he built will be next.

He’s an auto mechanic. He was a tour-bus driver for a while. He had no experience building tanks or working at a nuclear plant, but for six months last year, he was part of the team frantically trying to create new places for contaminated water to go.

Uechi and co-workers were under such pressure to build tanks quickly that they did not wait for dry conditions to apply anti-rust coating over bolts and around seams as they were supposed to; they did the work even in rain or snow. Sometimes the concrete foundation they laid for the tanks came out bumpy. Sometimes the workers saw tanks being used to store water before they were even finished.

“I must say our tank assembly was slipshod work. I’m sure that’s why tanks are leaking already,” Uechi, 48, said from his hometown on Japan’s southern island of Okinawa. “I feel nervous every time an earthquake shakes the area.”

Officials and experts and two other workers interviewed by the Associated Press say the quality of the tanks and their foundations suffered because of haste — haste that was unavoidable because there is so much contaminated water leaking from the wrecked reactors and mixed with ground water inflow.

“We were in an emergency and just had to build as many tanks as quickly as possible, and their quality is at bare minimum,” said Teruaki Kobayashi, an official in charge of facility control for the plant operator, Tokyo Electric Power Co.

Leaks and other flaws found in several tanks have raised concerns about further and more damaging failures, particularly if a big earthquake, tsunami or typhoon hits. The plant suffered a triple meltdown after Japan’s devastating 2011 earthquake and tsunami.

The plant has substantially stabilized, but decommissioning is expected to take decades, and TEPCO has suffered what Industry Minister Toshimitsu Motegi has described as a “whack-a-mole” succession of mishaps.

The environmental effects of radioactive water pouring in the sea are unclear, though scientists generally agree that the impact so far has been minimal. With years of work ahead, TEPCO is trying to contain as much contaminated material as possible.

Kobayashi acknowledged the need to improve the design of tanks and their foundations when they are replaced with more durable welded-seam tanks.

The plant has more than 1,000 tanks and other containers storing 370,000 tons of partially treated but still highly contaminated water. About one-third of the containers are easy-to-assemble steel tanks with rubber-sponge seams tightened with bolts; they were always considered a stopgap measure. The other tanks are considered sturdier.

The company is in the process of replacing rubber-seam tanks with larger, more permanent welded tanks, and expects to phase out the temporary tanks by March 2016. It intends not only to replace tanks intended for temporary use but to increase storage capacity to 800,000 tons.

TEPCO has recently accelerated its construction of more reliable tanks, but announced Friday that the pace will continue to be stepped up. “The worst scenario is we run out of space, and we must avoid that,” TEPCO President Naomi Hirose said at a news conference.


Print
Add This


MORE IN NEWS MORE IN NEWS >
EDITORS' PICKS

OHIO.COM VIDEOS

Prev Next
RealEstate
Loading...
Ohio.com Real Estate Listing Image
Norton
$154,900
Ohio.com Real Estate Listing Image
Akron
$369,900
Ohio.com Real Estate Listing Image
Hudson
$299,900
Ohio.com Real Estate Listing Image
Cuyahoga Falls
$245,000
Ohio.com Real Estate Listing Image
North Canton
$234,900
Ohio.com Real Estate Listing Image
Green
$169,900
Ohio.com Real Estate Listing Image
Akron
$695,000
Ohio.com Real Estate Listing Image
New Franklin
$159,900
Ohio.com Real Estate Listing Image
Hudson
$286,900
Ohio.com Real Estate Listing Image
Stow
$189,900
Ohio.com Real Estate Listing Image
Hudson
$249,900
Ohio.com Real Estate Listing Image
Russell Township
$365,000
Ohio.com Real Estate Listing Image
Wadsworth
$424,900
Ohio.com Real Estate Listing Image
Canton
$179,900
Ohio.com Real Estate Listing Image
Copley
$349,000
Ohio.com Real Estate Listing Image
Massillon
$179,900
Ohio.com Real Estate Listing Image
Akron
$269,900
Ohio.com Real Estate Listing Image
Hudson
$329,000
Ohio.com Real Estate Listing Image
Hudson
$475,000
Ohio.com Real Estate Listing Image
Cuyahoga Falls
$499,900

Most Read Stories